Project Updates
Water meters throughout the service area have been installed. A project to construct a water treatment plant is underway, although work is paused until summer for site conditions to improve. A project to replace the water mainline is being planned. A one-mile first phase has been designed, however, construction will not begin until a new source of funding is identified. Summary information about the projects is available in two fact sheets and summarized below.
Project Facts: Water Treatment Plant and Meters Installation (April 2026)
Water Meters Installation
The installation project is now completed. The new water meters will support better management of water use and improve the Company’s ability to identify and address leaks in the system. Throughout the park, each residence now has a new meter that can be read remotely. Immediately next to each meter box is a new round single valve box where the supply can be turned on or off to each residence.
NOTE: All equipment, including the older valve boxes, the meters and the new single valve boxes, is Company property. Customers are advised to install their own shut-off valves with the ability to drain interior plumbing on their own property as needed for winterizing.
However, customers will continue to have indefinite access to the new single valves.
Only personnel authorized by the Water System Operator have access to the new meter boxes and the older valve boxes. NO CUSTOMER ACCESS.
If you have a question or concern about any of the equipment, please call Sierra Park Water Company at (928) 445-5606, or email Hello@SierraParkWater.com.

Water Treatment Plant
This project will install an oxidation and filtration treatment system to eliminate iron and manganese, which are naturally occurring contaminants in the ground water, from the drinking water in Sierra Park. In addition to constructing a one-story building (approx. 24’ x 50’) to house the new system, the project also includes installing backwash and waste storage tanks, improvements to Wells 5 and 6 and automation of the existing water storage tank and well operations.
Sierra Park Water Company has awarded a contract to Innovative Construction Solutions in the amount of $2,199,000 with funding from the State of California, State Water Resources Control Board, Division of Drinking Water and the US Environmental Protection Agency with funding from President Biden’s Infrastructure Bill. Equipment manufacturing and work on-site has begun and completion is expected by the end of 2027.
Water Main Replacement
A project to replace the water main is being planned to improve the condition, reliability and operability of the water system. The main line and service lines are approaching 50 years of age and were constructed using materials suited for lower pressures than what the system operates under. At 4-inches in diameter, the existing mainline is also limited in how much water can be delivered. To support long-term reliability of the system and to provide adequate fire flows throughout the service area, the mainline and hydrants need to be replaced and upgraded throughout the service area.
Sierra Park Water Company held a town hall meeting on April 18, 2026 to review the project’s need and hear from the community. The main points from this meeting are mentioned below as FAQs.
FAQs
Condition and hydraulic limitations of the existing infrastructure: The main line and service lines are approaching 50 years of age and were constructed using materials suited for lower pressures (40-60 pounds per square inch or psi) than what the system operates under (up to 100 psi). At 4-inches in diameter, the mainline is also limited in how much water can be delivered.
Reliability and Operability: To support long-term reliability of the system and to provide adequate fire flows throughout the service area, the mainline and hydrants need to be replaced and upgraded throughout the service area.
State law (SB 522) requires that no later than January 1, 2032, the water system must have source system capacity, treatment system capacity if necessary, and distribution system capacity to meet fire flow requirements (Water Code §10609.62).
The local fire authority, in this case Tuolumne County, has jurisdiction over fire flow requirements for the system. While state regulations establish general expectations for water systems, the applicable fire flow requirements and whether upgrades are required are determined and enforced at the local level by the fire authority. Tuolumne County Fire Department, the local fire authority, is not requiring system-wide upgrades to meet current fire flow standards.
This is consistent with correspondence that informed the 2016 Water System Condition Assessment Report, which identified limitations relative to typical fire flow criteria. The reported noted:
“As discussed in Section 1, the water distribution system consists mainly of 4-inch diameter water pipelines with 2-1/2-inch diameter hydrants. Typically, a minimum of 6-inch diameter water mains and standard hydrants are required in order to supply the required fire flow of 1,000 gpm out of a single hydrant while maintaining a minimum pressure of 20 psi throughout the system, per the 2013 California Fire Code Section B105.1. In 2014, a fire flow test was conducted by County of Tuolumne Fire Prevention staff. The fire flow test was conducted at
two hydrants, one at the highest elevation in the system on Rebekah Road and one at the lowest elevation in the system on Jordan Way West. Results of the fire flow test showed that the maximum flow rate available at Jordan Way West while maintaining 20 psi at the hydrant
is 455 gpm. There was insufficient pressure at the Rebekah Road hydrant to determine the maximum flow rate available at 20 psi at the hydrant. Excessive head loss through the 4-inch diameter water pipelines will contribute to reduced flow and pressure at hydrants throughout the system. Insufficient fire flows put the community at risk during the event of a fire emergency.In order to achieve the required fire flow, a minimum of 6-inch diameter pipe and standard fire hydrants are needed. Per SPWC staff, there are approximately three isolation valves on the eastern side of the system that are inoperable. Additionally, there are three
hydrants that need replacement due to limited accessibility.”
Sierra Park Water Company will confer with the California State Water Resources Control Board Division of Drinking Water to gain a better understanding of how SB 552 applies to this water system. Follow-up will also be made with the Tuolumne County Fire Department to receive clarification and updated information about applicable requirements.
While the existing water system includes some looped segments, portions of the system still function with limited interconnection, reducing overall operational flexibility. Adding pipeline looping to a water distribution system significantly improves reliability, redundancy, and performance. By interconnecting pipelines, water can reach customers from multiple directions instead of relying on a single path. Expanding looping in the system allows operators to isolate breaks or perform maintenance without shutting off large portions of the system, maintaining service to most users. It also provides redundancy, so if one pipeline fails, water can still be delivered through alternate routes, an important benefit for aging infrastructure.
Looping improves pressure and flow distribution, reducing head loss and helps maintain more consistent service levels, particularly in areas currently served by long or undersized pipelines. It can also enhance fire flow availability by providing multiple supply paths.
Overall, additional looping increases system flexibility, reduces service disruptions, and strengthens long-term reliability and resilience, even when upgrades are not mandated. (See the Phase 2 diagram on the last page of this fact sheet.)
The project will be built when funds are available and will most likely be constructed in phases. The first phase would begin at Tank 210, located in the southeastern part of the service area. This is the primary storage tank that delivers water into the high pressure looped system into and around the
service area. Beginning the work at this location is the most direct way to improve water delivery into the system and to the customers. The project would install a new 8-inch pipe at the outlet of Tank 210 and extend down the unpaved access road toward the residential street of Isaac and then in a Water Main Replacement April 2026 northerly direction along Abraham. This route was chosen to work toward the center and then to the west side of the service area to reach the greatest number of service connections and hydrants.
Construction will involve excavation of a trench to install a new main line. The existing line would be abandoned in place. Most of the excavation for the new main line would be within the existing paved roads. Specifications would backfill and patch over the trench. The Water Company will work with the Odd Fellows Sierra Recreation Area to coordinate road maintenance work in a manner that is the most effective and efficient approach.
Grant funding from the State Department of Water Resources paid for the design of the first phase of the project to replace about one mile of main line and produced a set of plans that were advertised for construction. Seven bids were received; however, insufficient funding was available to award a construction contract of approximately $1.25 million.
The Water Company will seek additional sources of funding to complete this project, which will require additional planning/design and construction funding for the main line that extends approximately five miles in total throughout the service area.
Sierra Park Water Company will work with the DWR and Tuolumne County Fire to clarify the regulatory requirements specific to this system and will explore opportunities to pursue additional funding through grants or low-interest loans to complete the main line replacement.
The report prepared for Sierra Park Water Company by Black Water Consulting Engineers is available on the website by following this link: Condition-Assessment-Report-Final
How Do I…?
Tank Maintenance
Major Tank Renovation Completed
A project to rehabilitate the 210,000-gallon water storage tank located at the southeast end of Sierra Park has been completed. This $278,000 project included interior renovation, exterior overcoating and numerous safety, sanitary, security and structural repairs. The work was performed by Superior Tank Solutions and was completed in mid-August. For more information, download the Project Completion Report (08/12/2025).
Please direct any and all questions to Sierra Park Water Company email to Hello@Sierraparkwater.com